1) explosive quantity calculating

炸药量计算
2) charge calculation

药量计算
1.
In order to calculate the chamber charge of the 3~(rd) stage upriver RCC cofferdam of the Three Gorges Project,some formulas are analyzed and compared,some reasonable factors are used for reference,and a charge calculation formula of deep-water chamber blasting is put forward,which has been applied in the demolishing design of the 3~(rd) stage cofferdam in Three Gorges Project.
为计算三峡三期上游RCC围堰药室药量,通过对常用硐室爆破药量计算公式的分析和比较,吸取各公式的合理之处,在露天硐室爆破经典公式的基础上,得出了深水硐室爆破药量计算公式,并应用于三峡三期上游RCC围堰倾倒法爆破拆除设计中。
3) explosive metering device

炸药计量装置
4) explosive de-sign

炸药设计
5) projectile filling

微量炸药
6) blast charge

爆炸药量
补充资料:计算机断层扫描法测定骨量
计算机断层扫描法测定骨量
本法适用于测定腰椎骨量,但放射剂量较高。
说明:补充资料仅用于学习参考,请勿用于其它任何用途。
参考词条